 
          
            
              46
            
          
        
        
          
            Geotechnical News • June 2016
          
        
        
        
          
            GROUNDWATER
          
        
        
          two other reasons were retained in the
        
        
          1980s field investigations following
        
        
          the poor performance of the liners.
        
        
          The results of the two full-scale leak-
        
        
          age tests showed that the leakage was
        
        
          reduced when the water levels reached
        
        
          mid-slope. Because the water thick-
        
        
          ness above the liner had been halved,
        
        
          the leakage rate should have been
        
        
          roughly halved. However, this was
        
        
          not the case. Leakage rates were only
        
        
          1-2 mm/d (these small values were
        
        
          inaccurate) and thus, much less than
        
        
          half the leakage rate at full water level.
        
        
          These findings led the author, acting
        
        
          as an expert in the 1980s, to suspect
        
        
          that mid-slope pipes were improperly
        
        
          sealed or the upper parts of the liners
        
        
          were too permeable.
        
        
          A possible indication of damage in
        
        
          the upper parts of the liners was found
        
        
          in the July report of the construction
        
        
          inspector who reported cracking in
        
        
          the upper slopes. The engineer then
        
        
          requested a verification that the cracks
        
        
          would not be more than 3 to 5 cm
        
        
          deep, otherwise the contractor would
        
        
          have to spray water to increase the
        
        
          clay water content, re-mix the 15-cm
        
        
          clay lift, and re-compact it. This may
        
        
          have been done, but there was no writ-
        
        
          ten evidence of this in subsequent field
        
        
          reports. In addition, the two lagoons
        
        
          did not receive rain water or water
        
        
          spraying during weeks between the
        
        
          end of their construction and the full-
        
        
          scale leakage tests. This situation was
        
        
          physically detrimental to the liners.
        
        
          A few weeks after the full-scale tests,
        
        
          all participants in the project agreed
        
        
          to empty the two lagoons. This was
        
        
          needed so that the reasons for the poor
        
        
          performance could be investigated.
        
        
          
            Field verifications of the liners
          
        
        
          
            and pipes
          
        
        
          After the full-scale leakage tests, the
        
        
          lagoons were emptied for inspection.
        
        
          Shelby clay samples were taken in the
        
        
          upper slopes. The liner thickness in
        
        
          the upper slopes, supposed to be 75
        
        
          cm, was only 45 cm on average for
        
        
          liner No. 1, and 40 cm for liner No. 2.
        
        
          The measured values ranged from 29
        
        
          
            Figure 2 Full-scale leakage test, lagoon 1: (a) water level versus time; (b)
          
        
        
          
            non–dimensional graph of relative flow rate Q/Qmax versus relative water
          
        
        
          
            thickness h/hmax for the same lagoon geometry.