 
          
            
              42
            
          
        
        
          
            Geotechnical News •  December 2019
          
        
        
        
          
            THE GROUT LINE
          
        
        
          pictures in fig. 8) of the discovered
        
        
          columns) and to set up the operational
        
        
          parameters (flow rate and pressure of
        
        
          grout and air, uplift velocity, rotational
        
        
          speed) after the treatment energy pro-
        
        
          cedure (Tornaghi et al. 2004).
        
        
          In order to allow a more regular high
        
        
          pressure injection during the uplift
        
        
          phase, even in presence of boulders,
        
        
          each column execution was preceded
        
        
          by a predrilling, carried out 1 m down
        
        
          into the bedrock, by means of a dedi-
        
        
          cated drilling unit.
        
        
          Some preliminary pre-drillings along
        
        
          the columns’ alignment (for the cof-
        
        
          ferdam as well as for the impervious
        
        
          curtain) were initially made, in order
        
        
          to detect the bedrock level and hence
        
        
          to draw an accurate profile of the allu-
        
        
          vial deposit base.
        
        
          The geometry of the treatment
        
        
          involved the execution of inclined
        
        
          columns at the two ends of the curtain,
        
        
          with drillings made with angles up to
        
        
          43° from the vertical.
        
        
          During the treatment of the cofferdam,
        
        
          the steel pipe reinforcement was usu-
        
        
          ally inserted in the hole made for the
        
        
          jet grouting.
        
        
          The effect of the treatment was suc-
        
        
          cessfully tested during the excavation
        
        
          for the plant construction. The picture
        
        
          in fig. 9 shows on the left the jet
        
        
          grouted wall that separates the
        
        
          riverbed from the area of the site
        
        
          for the power house and the gates
        
        
          building. No significant water income
        
        
          from the waterproofed embankment
        
        
          occurred.
        
        
          On the right –
        
        
          The road on the
        
        
          crown of the
        
        
          embankment,
        
        
          used for the site
        
        
          traffic
        
        
          This allowed for
        
        
          completion of
        
        
          all the activities
        
        
          for the power
        
        
          plant construc-
        
        
          tion (from the
        
        
          embankment con-
        
        
          struction to the test on the turbine) in
        
        
          18 months without any interruption. In
        
        
          case of seasonal interruption (without
        
        
          the waterproofing of the cofferdam),
        
        
          6 additional months should have been
        
        
          considered. Until today, during the
        
        
          works for the five plants completed,
        
        
          only on one occasion the river has
        
        
          overflowed the embankment, causing
        
        
          a flood that interrupted the works. The
        
        
          site was evacuated on time, thus limit-
        
        
          ing the damages. Two months were
        
        
          necessary for restoring the yard.
        
        
          
            Rock grouting
          
        
        
          The treatment of the rock for the
        
        
          impervious curtain was carried out
        
        
          using the MPSP (Multiple Packer
        
        
          Sleeve Pipe) system. After the hole
        
        
          was drilled, a
        
        
          Ø
        
        
          1”1/2 PVC TAM
        
        
          pipe (40/48 mm inner/outer diameter)
        
        
          was installed. The TAM pipe was
        
        
          equipped, every 3 to 5 meters, with
        
        
          several Heavy Duty Obturator Bags,
        
        
          made in polypropylene geotextile and
        
        
          mounted on one or two sleeves. The
        
        
          bags were initially folded and fixed to
        
        
          the pipe at the ends by a metallic tie
        
        
          (see fig. 10). The tube was centred by
        
        
          means of plastic collars.
        
        
          Once the pipe was in place, the bags
        
        
          were filled with injected cement grout
        
        
          (ratio W/C=0.6:1) by a double packer
        
        
          lowered to one of the correspondent
        
        
          sleeves, and finally sealing the annular
        
        
          space between the plastic pipe and
        
        
          the borehole. Under the pressure of
        
        
          the injection, the cement of the grout
        
        
          separated from the water, being the
        
        
          latter ejected per seepage through the
        
        
          geotextile. As a result, the hole was
        
        
          divided into several stages by means
        
        
          of the tough sealings obtained inject-
        
        
          ing each obturator bag; a curing time
        
        
          of 18-24 hours were sufficient for the
        
        
          aim (see fig. 11).
        
        
          The grouting of each stage was then
        
        
          made with the conventional MPSP
        
        
          injection procedure. The double
        
        
          packer was placed astride one of the
        
        
          sleeves of the deeper sector, but in this
        
        
          case no plastic sheath was necessary.
        
        
          In fact, the grout filled initially the
        
        
          annular void between the pipe and the
        
        
          borehole, and then it flushed into the
        
        
          fissures intercepted by the hole stage.
        
        
          The injection was then carried out
        
        
          following the prescribed rules for
        
        
          the rock treatment. The curtain was
        
        
          formed by two alignments of TAMs,
        
        
          spaced 1.50 m (5ft) and with interaxis
        
        
          of 1.50 m (5ft) between the boreholes.
        
        
          In a first phase primary pipes were
        
        
          drilled and injected; then the second-
        
        
          ary pipes phase followed (fig. 12).
        
        
          Along the earth dam axes the holes
        
        
          were drilled passing through the jet
        
        
          grouted columns.
        
        
          The obturator bags were installed
        
        
          every 3 to 5 m (10 to 16 ft) in the pipe
        
        
          stretch into the rock to be treated.
        
        
          Another bag was mounted about 1 m
        
        
          
            Figure 9: On the left - Works in progress with the jet
          
        
        
          
            grouting wall protection from the river bed.
          
        
        
          
            Figure 10: Folded and injected
          
        
        
          
            obturator bags mounted astride a
          
        
        
          
            manchette.
          
        
        
          
            Figure 11: Scheme of the MPSP
          
        
        
          
            system grouting.